17.04.07 reno update

Electrical work done. Plumber still at work when I visit flat at 6.15pm. A very nice uncle who has no attitude. I've asked him to help me to 'seal' up my new toilet bowl @MBR toilet, he did it immediately. Told me he will finish the main part of plumbing and the touch up / rest of minor installation will do on later part of reno. Stainless steel piping should all up by tonight.

Checked the hacking of living balcony floor done by h*b, also swee swee le. Thank goodness nothing bad happened in the process... was afraid they cracked the balcony glass or spoil the balcony door thread lah.. kekez..

False ceiling boards are placed in the flat already. According to revised project schedule, which Colin has updated, wed and thurs will be doing of false ceiling works. Tiling will start on Thurs!! Tomorrow got to go back to put Tong(2) Ban(3) - coin onto the floor, for tiler to put cement on, under the tiles... suppose to bring fortune. Believe it or not, no harm doing right?